Prepare for a pull planning session
Pick the milestone, invite the right people, and set up the Timeline before anyone arrives.
A week or two before
- Pick one milestone and write down what "done" means for it: the conditions that must be true. "DD set issued to the owner, coordinated with structure and MEP, cost check complete" beats "DD done".
- Invite the people who do the work, not only their managers: each discipline or trade lead, the owner's representative and anyone who makes decisions the plan depends on. Two to three hours, in person if you can.
- Choose a facilitator who doesn't own the work being planned. They keep the room moving; see Facilitator tips.
- Ask everyone to bring their honest durations, what they need from others, and what's worrying them.
Set up 7SecondOS
- Open the project's Schedule and switch to Timeline.
- Add a lane for each discipline or trade with + Lane, so each note sits with whoever delivers it.
- Add the milestone as a note in its due-date column, open it (double-click) and tick Locked due date so nothing pushes it.
- Add the people coming to the project's team, and invite outside consultants as guests, so they can see the plan after the session. See People on a project.
- Log what you already know could get in the way (a pending owner decision, a long-lead item) in the RAIDD Log, so it's on the table from the start.
Send before the session
- The milestone and what "done" means.
- The agenda (see Run the session) and how long it will take.
- A link to the project, so people can look at the Timeline beforehand.