The critical path is the chain of tasks that sets when the project finishes. If a task on it slips a day, the finish slips a day. Every other task has float: the days it can slip before it would hold up the finish. 7SecondOS works it out from your links, backwards from the finish, the way MS Project and Primavera do.
Show it on the Gantt
- On the Schedule's Gantt, click Critical path in the toolbar.
- Critical tasks and milestones turn coral, and so do the links between them. Phase bars don't change.
- Every other task shows its float as a dashed line after its bar, to the last day it can finish. Hover a bar to read it ("5 work days of float").
- To see the path to one milestone instead of the finish, pick it in the dropdown next to the button (to the project finish ▾). Only the tasks that lead to that milestone are coloured; the rest get no float.
- Click Critical path again to hide it. It's remembered for you on this project, in this browser.
Columns, filters, print and Excel
- Customize (Gantt or List) has a Float column (days, coral when 0 or less) and a Critical column.
- In the Timeline, Board, Calendar and Takt view, More filters → Critical only shows just the critical tasks.
- Print has Show the critical path (ticked when the Gantt shows it). Excel always has Float and Critical columns.
- Ask about the project knows the critical path too, so you can ask "what's driving the finish?".
How it's worked out
- It follows your links (finish-to-start, with their lag). A task with no link after it can run up to the project finish, so it often has a lot of float: link your tasks so the path means something.
- Float is counted in work days when the schedule counts work days, otherwise in calendar days.
- Done tasks are left out: they can't slip any more.
- A locked due date is a deadline the task can't move past, so a locked task is always critical. If the work before it can't make that date, it shows negative float ("3 days behind"): the plan can't be met as it stands.
- A link into a phase holds back every task in it; a link out of a phase waits for all of them.
- It's worked out again with every change, for everyone, so it always matches the schedule.