The Takt view shows the schedule as a takt plan: each row is a zone, each column a takt (a fixed length of time, such as five work days), and each task sits in its zone's row under the takt it starts in, coloured by its lane (the trade). On a good plan the trades make diagonal trains down the grid. For the method behind it, see What takt planning is.
Switch it on
- On the Schedule, click Zones in the toolbar (you need to be able to edit the schedule).
- Tick Use zones on this project if it isn't already, and set up your zones. See Zones.
- Tick Use takt planning. A Takt view appears next to Calendar.
- Open it and click Takt settings to set the takt length and the day takt 1 starts (empty: the Monday of the first task in a zone).
Work in it
- Drag a card to another cell: another zone, another takt, or both. It moves by whole takts and keeps its place within the takt; what waits on it moves too. A locked due date stays in its takt.
- Double-click a card to edit it, or an empty cell to add a task there, filling that takt.
- Give the tasks their trade with lanes: each lane's colour is the trade's colour in the grid.
- The filters work here too: Phase, Look-ahead, Zones, Lanes, Hide done.
- Every card is an ordinary task, so the Gantt, Timeline, List, Board and Calendar show the same change at once.
Build a train
A train is the trades that go through the zones one takt apart. The train builder lays every trade out in every zone at once, instead of one task at a time.
- In the Takt view, click + New train.
- Name it, pick the takt it starts in, and list its trades in order: what each does, its lane (the company doing it) and how many days it takes in one zone.
- Tick the zones it goes through and put them in order with ↑ ↓.
- Set a buffer (takts kept free at the end for what goes wrong).
- Check the summary and the balance (below), then click Build train.
- It makes one task per trade per zone, named like "Framing · Level 2 › East", under a phase named after the train, linked so each trade follows the one before it in a zone and moves from zone to zone in order. The buffer is a task of its own at the end.
- How long it takes: (trades + zones − 1) takts, then the buffer. Five trades through eight zones is 12 takts.
- The balance chart shows each trade's days in a zone against the takt (the line). A trade past the line is the bottleneck, in red: everything behind it waits, and the cards behind it run off beat. Add crew, split its work into two trades, or make the zones smaller.
- Click a train's chip to change it, then Build again. Cards already there keep their progress, notes and comments; they go back on the beat if they were moved by hand. Cards for a removed trade or zone are deleted.
- Delete train can delete its tasks too, or keep them as ordinary tasks.
- Balance ▸ at the bottom of the Takt view shows every train's balance.
- A project can have several trains, such as rough-in and finishes, sharing the same takt.
Reading it
- ✓ and faded: done. Red outline: late. Off beat: it runs past the end of its takt and holds up the trade behind it; hover to see by how much.
- Off-takt work (dashed) is never flagged: tick Off-takt work in a task's window for a one-off room, a delivery or anything else that doesn't follow the beat.
- The header shows the takt, today's takt (its column is shaded), PPC for the last finished takt (of the tasks due in it, how many are done), and how many cards are off beat or late.
Switch it off
Untick Use takt planning in the Zones window. The Takt view and the Off-takt work box disappear; nothing is deleted, and the rest of the schedule doesn't change.