Takt planning splits the building into zones of about the same amount of work and gives every trade the same fixed time in each one, the takt (say, five work days). When the time is up, every trade moves to its next zone at once. Framing is in Level 3 East while MEP rough-in is in Level 2 West and drywall is in Level 2 East: a train of trades moving through the building.

Why it works

  • A steady rhythm. Trades know weeks ahead where they'll be and when, so crews and deliveries can be planned to it.
  • Problems show at once. A trade that runs past its takt holds up the one behind it. In the Takt view it's marked off beat that same day, not at the end of the month.
  • Shorter, predictable phases. Once the train is running, a zone is finished every takt.
  • Less work in progress. Each zone has one trade in it at a time, so less gets damaged, reworked or lost.

Is it right for this job?

  • Yes for repeating areas: patient floors, typical office floors, hotel rooms, classroom wings, housing units. Interior fit-out on hospital jobs is a classic use.
  • Partly for jobs with a few repeating areas and many one-offs. Takt the repeating part and plan the rest on the Gantt or the Timeline as usual.
  • Not really for sitework, structure with very different areas, or short jobs with few trades.
  • Work that doesn't follow the beat (a one-off room, a delivery, an inspection with its own clock) can sit in a zone as Off-takt work. Tick it in the task's window and it's never flagged.

The playbooks

  1. Gather the data
  2. Set the zones and the takt
  3. Sequence and balance the trades
  4. Run it week to week
  5. Facilitator tips for takt

In 7SecondOS, takt planning is optional per project: switch it on in Zones in the Schedule's toolbar, and a Takt view appears next to Calendar. See The Takt view.