Zones
- Make zones of about the same amount of work, not the same size. A zone full of exam rooms takes more MEP than an open office of the same area.
- On many interior jobs a zone is somewhere around 5,000 to 20,000 square feet: half a floor, or a floor. Smaller zones mean a faster train, but more handoffs.
- Follow the building: a level split at the core, a wing, a smoke compartment. Crews should be able to find the line.
- In 7SecondOS: Zones in the toolbar, + Add many levels… (Level 2 to 6, each with East and West), and type each zone's area. See Zones.
The takt
- Start with the trade that takes longest in a zone: the takt is about as long as it needs (or split its work so it fits).
- Common takts are a week (five work days), which suits weekly planning meetings, or one or two days on busy repeating work. Some hospital interior jobs have run one-day takts.
- Set it in the Takt view: Takt settings, the length, and the day takt 1 starts. The train builder shows each trade's days against it.
How long the phase takes
With W trades (the "wagons" of the train) and Z zones, the last trade leaves the last zone after (W + Z − 1) takts. Five trades through eight zones at five days a takt: (5 + 8 − 1) × 5 = 60 work days. Add a buffer at the end of the phase, often one takt, for what goes wrong.