Put the trades in order, then even out the one that can't keep up.
Sequence
Put the trades in order for one zone, with the people who do the work, as in a pull planning session: what does each need before it starts?
Build it as a train in the Takt view (+ New train): every trade in every zone, one takt later each time, linked in order. In the grid the tasks make a clean diagonal.
Balance
A trade whose work in a zone takes longer than the takt is the bottleneck. In the Takt view its card is marked off beat, and everything behind it waits.
Fixes, from easiest: add crew for that trade; split its work into two wagons (rough-in top-out and rough-in walls); move work to a trade with slack; resize the zones so each holds less of that work.
A trade that takes much less than the takt has slack. That's fine; it can absorb a bad day or take on work from the bottleneck.
Some trades work alongside others in a zone. Give each its own task in the zone; they can share a takt.
In 7SecondOS
In the Takt view, click + New train and list the trades in order, each with its days in one zone.
Watch the balance chart as you type: a red bar is the bottleneck. Fix it in the builder (more crew means fewer days; split the trade into two) before building.
Pick the zones in order, add a buffer, and click Build train. Every trade lands in every zone, one takt apart, linked in order.
Changed your mind? Open the train again, change it, and Build again. Progress and notes stay.