Short huddles, promises kept by takt, and fixing off-beat work before it spreads.
Every takt (or every day on short takts)
Huddle at the Takt view with the foremen. Filter to the coming takts: Look-ahead next 3 or 6 weeks, and Zones if the job is big.
Check each card in this takt column: done (tick it), on track, or in trouble.
Fix anything off beat now. Move a card to where it can really happen (drag it to another takt or zone), add crew, or split the work. What waits on it moves with it.
Make sure the next takt is ready: inspections booked, material there, the zone clear. Anything that isn't goes in the RAIDD log, linked to the task.
Keep score
The Takt view shows PPC (percent plan complete) for the last finished takt: of the tasks due in it, how many were done. Above about 80% the train is running; below, look for why.
Count the off beat cards each takt. Fewer each week means the plan is getting better.
The Pull Plan Coach can follow up on the promises every week and ask why the missed ones slipped.
When it slips
Use the buffer at the end of the phase first. Don't move the whole train for one bad day.
If one zone keeps falling behind, look at its size and work again. It may need splitting (Split in the Zones window, which can copy its tasks and links into the new half).
If the whole train runs slow, the takt may be too short. Change it in Takt settings; no task moves, only which takt each falls in.