A takt plan is only as good as the numbers behind it. Collect them first, trade by trade, for the part of the building you'll takt.
- List the trades in the order they work, one area at a time: framing, MEP rough-in, inspections, insulation, drywall, tape and finish, prime and paint, ceilings, flooring, trim-out.
- For each trade, get the quantities per floor or area: linear feet of wall, fixtures, devices, square feet of board.
- Ask each foreman how many people they'd put on it and how many days that takes for a typical area. Their numbers, not yours.
- Note what each trade needs before it can start in an area (an inspection, a delivery, a decision) and what holds it up today.
- Write down the hard dates: inspections that need booking, long-lead equipment, owner moves.
- In 7SecondOS, make a lane for each trade (Timeline or Board, + Lane). The lanes become the colours of the train in the Takt view.
- A Canvas board with one sticky note per trade, quantities and durations on each, is a quick way to collect this in a meeting.