A takt plan is only as good as the numbers behind it. Collect them first, trade by trade, for the part of the building you'll takt.

  1. List the trades in the order they work, one area at a time: framing, MEP rough-in, inspections, insulation, drywall, tape and finish, prime and paint, ceilings, flooring, trim-out.
  2. For each trade, get the quantities per floor or area: linear feet of wall, fixtures, devices, square feet of board.
  3. Ask each foreman how many people they'd put on it and how many days that takes for a typical area. Their numbers, not yours.
  4. Note what each trade needs before it can start in an area (an inspection, a delivery, a decision) and what holds it up today.
  5. Write down the hard dates: inspections that need booking, long-lead equipment, owner moves.
  • In 7SecondOS, make a lane for each trade (Timeline or Board, + Lane). The lanes become the colours of the train in the Takt view.
  • A Canvas board with one sticky note per trade, quantities and durations on each, is a quick way to collect this in a meeting.